Equipment Diagnostics Service

Assessing equipment condition to prevent failures and extend asset life

Engineering Cost
Industrial piping and equipment being assessed for condition

Non-destructive testing and remaining-life evaluation preventing failures

JERA's Equipment Diagnostics Service combines non-destructive testing (e.g. borescope inspection) with your operation and inspection data to judge equipment integrity, remaining life, and fitness for service — a user-side second opinion to conservative OEM advice. It prevents failures like boiler tube leaks, cuts cost by replacing only what's needed, and extends equipment life.

Request a consultation Guide coming soon

Issue

  • Frequent equipment failures

  • Limited asset health visibility

  • Rising O&M costs from equipment stress

AT A GLANCE

70+ years

Operating thermal power plants worldwide

WHY JERA

A user's second opinion, not a vendor's

JERA evaluates from an operator's view — for example, holding scale-behavior data across tube materials — more precise than conservative OEM calls.

OVERVIEW

What is Equipment Diagnostics Service

Equipment Diagnostics Service evaluates the integrity and remaining life of your plant's critical equipment. Combining non-destructive testing — such as borescope inspection — with your operation and inspection data, JERA performs an equipment condition assessment and remaining life assessment, and judges fitness for service. As a user-side second opinion to conservative OEM advice, a leading example is boiler tube creep-life evaluation, and the same approach extends to other equipment.

BENEFITS

What health diagnosis delivers

  1. 01

    Improved availability

    Fewer unplanned shutdowns from equipment failures.

  2. 02

    Cost reduction

    Replace or repair only what the data shows is necessary — not the OEM's blanket list.

  3. 03

    Extended equipment life

    Keep sound equipment in service longer, backed by fitness-for-service evidence.

CASE STUDY

One tube replaced instead of many

Boiler tube life assessment

CHALLENGE

A coal plant suffered frequent boiler tube leaks — each forcing a ~7-day outage — and the OEM's conservative recommendations called for costly, wholesale tube replacement.

SOLUTION

As a second opinion, JERA evaluated creep life on three critical parts (3rd-stage SH, 2nd-stage RH, 3rd-stage RH). The 3rd SH (33%) and 2nd RH (49%) sat inside the OEM's replace range but did not need replacing by JERA's criteria; only the 3rd RH had reached 100%.

RESULT

Replacing just the one tube cut cost versus the OEM estimate. With online creep monitoring added, tube-leak outages fell sharply and repairs could be planned around scheduled stops.

Source: JERA project record at a power plant in the Philippines. Figures are from one site and vary by plant configuration and operation.

Q&A

Boiler tube leaks: Equipment Diagnostics Service, answered

Q. What is Equipment Diagnostics Service for boiler tube leaks?
A.

It evaluates boiler tube creep life (Boiler Predictive Management) using your operation, drawing, and inspection data with JERA's proprietary formula. As an operator itself, JERA gives a user-based second opinion to conservative OEM calls — so you cut tube leaks, act only where needed, and extend tube life.

Q. How does online creep evaluation compare with spot (offline)?
A.

Spot (offline) evaluation is calculated from inspection results and past operating data, so it does not reflect the current operating state. Online evaluation responds to metal temperature and creep-life consumption as they change moment to moment, so it always computes the latest remaining life and lets JERA propose a more effective replacement plan.

Q. Beyond creep-life evaluation, what else does JERA do to reduce tube leaks?
A.

The causes of boiler tube leaks depend on plant operating conditions and design — thermal fatigue from boiler structure, insufficient water chemistry, and so on — and the countermeasures differ accordingly. JERA proposes measures matched to your plant's actual operating conditions, so please consult JERA first.

Catch equipment problems before they force an outage

Request a consultation. Share your equipment data and JERA will diagnose its health as a second opinion — for example, evaluating boiler tube creep life to show where action is truly needed and how to cut unplanned outages, before you commit.