Mesaieed Gas Thermal IPP ProjectOur Company / Investment Projects

Mesaieed Gas Thermal IPP Project QATAR

In 2008, Chubu Electric Power Company (“Chubu”) constructed a 2,000MW gas thermal power plant to maintain and operate in the Mesaieed Industrial Area of Qatar, located approximately 40km south of the capital Doha. In this project, the electricity generated is sold to Qatar General Electricity & Water Corporation (Kahramaa) over a 25-year period. Of the 2,000MW, 1,000MW began operation in 2008 and the remaining 1,000MW began operation in 2010. As the long-term power purchase agreement is guaranteed by the Qatari government, the project is considered a solid investment and stable source of revenue over the long-term.

Project Outline

Company name
Mesaieed Power Company
Location

Mesaieed Industrial Area (Approx. 40km south of the capital Doha)

Map
Power output
2,000MW (as of March 2018)
Power generation method
Combined-cycle
Fuel
Natural gas
Operating since
Some operations began in 2008, overall start of operations began in 2010
Investors
JERA, Qatar Electricity & Water Company,Qatar Petroleum,Marubeni

Project company’s homepage