JERA acquired an equity interest in the Formosa 1 offshore wind power project, located off the north-western coast of Taiwan. It consists of 22 fixed-bottom offshore wind power generators and began operations in April 2017.

The 128MW Formosa 1 project represents Taiwan’s first utility-scale offshore wind farm. The first phase of 8MW has been successfully operated since April 2017, with the additional 120MW under construction expected to start operations in late 2019. The project has secured the support of Taiwan Power Company under a 20-year Power Purchase Agreement based on the FIT (Feed in Tariff) scheme.

Outline

Phase 1 Phase 2
Company Name Formosa I Wind Power Co., Ltd.
Location

map
Generation Type Offshore Wind Power Generation
Generation Capacity 8MW 120MW
Number of Generators 2 Units 20 Units
Commercial Operation Date April 2017 By end of 2019
Investors Investors JERA, Ørsted A/S, Macquarie, Swancor