Decommissioning Units 1 through 3 at Oi Thermal Power Station, Units 5 and 6 at Yokohama Thermal Power Station, and Units 1 through 4 at Chita Thermal Power Station2022/03/31

JERA Co., Inc. (“JERA”) has today decommissioned Units 1 through 3 at Oi Thermal Power Station, Units 5 and 6 at Yokohama Thermal Power Station, and Units 1 through 4 at Chita Thermal Power Station (total 3,833MW), all of which have been under long-term planned shutdown.

 

JERA is currently moving forward with replacement work at thermal power plants in other locations (total 6,660MW)1. With the understanding and cooperation of local communities and other stakeholders, JERA is making every effort to secure a stable supply of energy.

 

Overview of Oi Thermal Power Station

・Location: 1-2-2 Yashio, Shinagawa-ku, Tokyo-to

Unit no.

Generation capacity

Generation type

Fuel

Start of Operation

Decommissioning

Unit 1

350MW

Steam

Crude oil

August 1971

March 2022

(Shutdown since April 2016)

 

Unit 2

350MW

February 1972

Unit 3

350MW

December 1973

 

 

Overview of Yokohama Thermal Power Station

・Location: 11-1 Daikoku-cho, Tsurumi-ku, Yokohama-shi, Kanagawa-ken

Unit no.

Generation capacity

Generation type

Fuel

Start of Operation

Decommissioning

Unit 5

175MW

Steam

    LNG

March 1964

March 2022

(Shutdown since April 2016)

Unit 6

350MW

June 1968

Unit 7-1

377MW

Combined cycle

LNG

January 1998

Unit 7-2

377MW

October 1997

Unit 7-3

377MW

January 1997

Unit 7-4

377MW

June 1996

Unit 8-1

377MW

July 1996

Unit 8-2

377MW

February 1997

Unit 8-3

377MW

October 1997

Unit 8-4

377MW

January 1998

 

Overview of Chita Thermal Power Station

・Location: 23 Kitahama-machi, Chita-shi, Aichi-ken

Unit no.

Generation capacity

Generation type

Fuel

Start of Operation

Decommissioning

Unit 1

529MW

Combined cycle (repowering)

LNG

February 1966

March 2022

(Shutdown since March 2017)

Unit 2

529MW

January 1967

March 2022

(Shutdown since April 2017)

Unit 3

500MW

Steam

LNG

March 1968

March 2022

(Shutdown since April 2017)

Unit 4

700MW

March 1974

March 2022

(Shutdown since October 2017)

Unit 5

854MW

Combined cycle (repowering)

LNG

March 1978

Scheduled for

FY 2026

Unit 6

854MW

April 1978

 

1 New Units 1 through 3 at Anegasaki Thermal Power Station, New Units 1 through 3 at Goi Thermal Power Station, New Units 1 and 2 at Yokosuka Thermal Power Station, and Unit 5 at Taketoyo Thermal Power Station