JERA Joins Forces with Hokkaido Electric and Tohoku Electric in the Ishikari Bay New Port Offshore Wind Farm Project in Hokkaido, Japan2025/10/01

JERA Co., Inc. (“JERA”) announced today that it has transferred a portion of its ownership interests in the Ishikari Bay New Port Offshore Wind Farm Project (“the Project”) through its renewable energy subsidiary JERA Nex Limited, to a newly established investment company formed by Hokkaido Electric Power Co., Inc. (“Hokkaido Electric”) and Tohoku Electric Power Co., Inc. (“Tohoku Electric”). Following the transfer on September 30, 2025, the project is now jointly operated by four companies: JERA, Green Power Investment Corporation (“GPI”), Hokkaido Electric, and Tohoku Electric.

 

Located at Ishikari Bay New Port in Hokkaido, the wind farm consists of 14 8 MW Siemens Gamesa Renewable Energy turbines with a total capacity of 112 MW. The project began commercial operation on January 1, 2024, with all electricity supplied to Hokkaido Electric Power Network, Inc. The facility also distinctively features a 180MWh battery storage system.

 

The project has been stably operated by JERA and GPI to date, with close collaboration with the local communities of Ishikari City and Otaru City to promote regional development. The participation of Hokkaido Electric, with its strong relationship with the Hokkaido community through stable power, and Tohoku Electric, which has more than 70 years of experience in stable power plant operations in the Tohoku and Niigata regions, the four partners will bring together their expertise and strengths, to create synergies for enhancing the long-term stability and efficiency of the offshore wind power business.

 

With the continued support of local stakeholders, the partners remain committed to contributing to regional economic development and the realization of a sustainable, decarbonized society.

 

Overview of Ishikari Bay New Port Offshore Wind Farm Project

Project Company Name

Green Power Ishikari GK

Location

Part of the port area at Ishikari Bay New Port, Hokkaido

Installed Capacity

8MW x 14 turbines = 112MW (Grid connection capacity: 99.99 MW)

Commercial Operation Start Date

January 1, 2024

Power Offtaker

Hokkaido Electric Power Network Co., Inc.

Power Supply Period

20 years

Investors

JERA Nex Limited (Scheduled to be transferred to JERA Nex bp Limited)

Hokkaido Electric Power Co., Inc.

Tohoku Electric Power Co., Inc.

Green Power Investment Corporation

 

 