Initiating Preparations for an Environmental Impact Assessment as Part of Reviewing Plans to Replace Sodegaura Thermal Power Station2025/06/18

JERA Co., Inc. hereby announces that it has begun preparing for an environmental impact assessment as part of its review of plans to replace aging facilities at its Sodegaura Thermal Power Station with state-of-the-art gas turbine combined cycle power generation facilities that will contribute to reducing CO2 emissions. 

 

By replacing aging thermal power generation facilities with those that are state-of-the-art, JERA will contribute to ensuring a stable domestic supply of electricity over the long term and to achieving a decarbonized society. 

 

Overview of the Sodegaura Thermal Power Station Replacement Plan Being Reviewed

 

Existing Facility (Current)

After Replacement*1

Location

2-1 Nakasode, Sodegaura City, Chiba Prefecture

Generation Type

Steam

(Unit 1–4)

Gas Turbine Combined Cycle

(New Units 1–3)

 

 

Generation Capacity

Unit 1: 600MW

           (long-term planned shutdown) *2

Unit 2: 1,000MW

Unit 3: 1,000MW

Unit 4: 1,000MW

 

 

Approx. 2,600MW

Fuel

LNG

LNG

 

 

Start of Operation

Unit 1: August 1974

          (long-term planned shutdown)

Unit 2: September 1975

Unit 3: February 1977

Unit 4: August 1979

 

 

New Units 1–3: FY 2032 or later

*1 Post-replacement power generation facilities are still being reviewed and may change based on further deliberation.
*2 The existing unit1 has been under long-term planned shutdown since February 2023.